為維護校園安全及環境清潔,擬進行除草作業,請勿於下列期間靠近施作區域周圍,並請校內行車注意停放位置及車輛安全。特此公告週知,造成不便之處,敬請諒察!
1、作業期間:自115年6月19日(週五)至6月21日(週日),上午7點至下午5點。共計3日。
2、預計修剪順序:(施作區域如下圖)
◎115年6月19日至20日:第1、6、7、2區。
◎115年6月21日:第3、4、5區。
如因天候因素影響而無法作業,則將順延施作,如有相關疑問,請洽事務組吳助理(分機:2420)。
To uphold campus safety and maintain environmental cleanliness, weed removal operations are scheduled. Kindly refrain from approaching the designated work areas during the specified period, and all campus drivers are urged to be mindful of parking locations and vehicle safety. This announcement is made for your awareness and understanding. We apologize for any inconvenience caused and appreciate your cooperation.
1. Operation Period: From June 19th, 2026 (Friday) to June 21st, 2026 (Sunday), between 7:00 AM and 5:00 PM daily, spanning a total of three days.
2. Anticipated Trimming Sequence (Work areas as illustrated below):
◎ June 19th to 20th, 2026: Zones 1, 6, 7, and 2.
◎ June 21st, 2026: Zones 3, 4, and 5.
Should adverse weather conditions impede the work, the operation will be postponed accordingly. For any inquiries, please contact Assistant Wu of the General Service Division at extension 2420.